At least five days of chip sealing is planned beginning July 24 on the mountain section of U.S. Highway 14A east of Lovell, and traffic delays of up to 20 minutes are expected.
The 9.7-mile …
This item is available in full to subscribers.
The Powell Tribune has expanded its online content. To continue reading, you will need to either log in to your subscriber account, or purchase a subscription.
If you are a current print subscriber, you can set up a free web account by clicking here.
If you already have a web account, but need to reset it, you can do so by clicking here.
If you would like to purchase a subscription click here.
Please log in to continue |
|
At least five days of chip sealing is planned beginning July 24 on the mountain section of U.S. Highway 14A east of Lovell, and traffic delays of up to 20 minutes are expected.
The 9.7-mile project begins at milepost 70.72, about 24 miles east of Lovell, and concludes at milepost 80.42. All road improvements are dependent upon favorable weather.
The $3.7 million Lovell-Burgess Junction pavement improvement project was completed in 2022, with the exception of chip sealing.
Prime contractor is Century Companies, Inc., of Lewistown, Montana.
“We have been waiting for the weather to be warm enough on top of the mountain to chip seal this year,” said Wyoming Department of Transportation project engineer Jordan Erz of Worland. “Normally, it's warm enough to chip seal highways by July 4, but this year it snowed up there on July 4.”