A $4.93 million project is scheduled to begin Monday along Cody’s Sheridan Avenue.
Weather permitting, work on the concrete rehabilitation project is scheduled to begin on the north side of …
This item is available in full to subscribers.
The Powell Tribune has expanded its online content. To continue reading, you will need to either log in to your subscriber account, or purchase a subscription.
If you are a current print subscriber, you can set up a free web account by clicking here.
If you already have a web account, but need to reset it, you can do so by clicking here.
If you would like to purchase a subscription click here.
Please log in to continue |
|
A $4.93 million project is scheduled to begin Monday along Cody’s Sheridan Avenue.
Weather permitting, work on the concrete rehabilitation project is scheduled to begin on the north side of Sheridan Avenue from 10th Street to 12th Street. The north side of the 10th Street and 11th Street intersections will be closed while traffic is carried, one lane in each direction, on the south side of Sheridan Avenue.
Phase 1 of the project — 10th Street to 14th Street — is required to be complete by June 15. The project will be shut down from June 16 through Aug. 23, said Wyoming Department of Transportation resident engineer Todd Frost of Cody
During work, Frost said a maximum of two intersections may be closed at any one time.
“Work will be completed on one side of the street while two-way traffic is carried on the other half,” he said. “Left turns will not be allowed through the work zone. Parking may not be allowed through the work zone, and a 10-foot width restriction will be in effect.”
Weekly public work progress meetings will be held at 10 a.m. every Tuesday between March 3 and June 9 at the Cody Club Room. Citizens and businesses are invited to these weekly meetings, where the prime contractor will answer questions and share a two-week schedule of upcoming work.
The Sheridan Avenue project includes removing and replacing existing damaged concrete slabs, resealing existing concrete joints, grinding and texturing existing roadway, upgrading Americans with Disabilities requirements at every street corner between 10th Street and Stampede Avenue, replacing broken curb and gutter and sidewalk, and upgrading wiring at traffic signals.
The project begins at U.S. Highway 14/16/20 milepost 51.78 — at the intersection of 10th Street and Sheridan Avenue in front of the Park County Courthouse — and it proceeds 1.2 miles on U.S. 14/16/20 to the intersection of 17th Street and Stampede Avenue on Greybull Hill.
Phase 2 of the project will start Aug. 24, and all work must be completed from Alger Avenue to 14th Street through grinding and texturing prior to winter shut down.
Work will continue with Phase 3, which will proceed from Alger Avenue to the end of the project and must be completed through concrete grinding and texturing prior to June 15, 2021.
The project will be shut down from June 16, 2021, through Aug. 23, 2021.
The final phase requires all remaining work to be completed by Sept. 30, 2021.
Prime contractor S&S Builders, LLC, of Gillette will be paid a $200,000 incentive if all project work is complete by June 15, 2021.